Forest Service orders an environmental assessment for the Sheep Creek rare earth project in the Bitterroot

After more than 6,500 comments, the Bitterroot National Forest dropped a quicker categorical exclusion and will do a full environmental assessment of Sheep Creek.

The Bitterroot River flowing past cottonwoods and grassy hills near Darby, Montana
The Bitterroot River near Darby. Photo: Forest Service Northern Region from Missoula, MT, USA / Wikimedia Commons, public domain

The Bitterroot National Forest will do a full environmental assessment of a proposed rare earth exploration project at the headwaters of the Bitterroot River. The decision drops the faster categorical exclusion the agency had been considering for the Sheep Creek site.

The forest announced the change on Nov. 20. It said more than 6,500 public comments, along with agency consultation and interdisciplinary review, “concluded the need for additional environmental analysis.”

What the company wants to do

US Critical Materials Corp. holds unpatented mining claims in the Sheep Creek drainage of the West Fork Ranger District in Ravalli County. According to the project’s listing on the federal permitting dashboard, the company wants to test the subsurface for gallium, samarium, scandium, neodymium and praseodymium, and to secure two existing historic mine adits.

The plan covers four locations: bulk sampling at one and diamond-core drilling at three. Crews would install temporary helicopter landing platforms, clear some vegetation, grade small pads and dig lined sumps to recirculate drill water. The listing says the work would disturb about 0.3 acres, take less than a year with a winter shutdown, and involve no road building, ore processing or commercial extraction.

Opponents see it differently. The Daily Montanan reported that the project calls for removing 3,000 short tons of material from an area that is sensitive for wildlife and feeds the Bitterroot Valley’s water. Earlier reporting by the same outlet described an operating plan with 2,200 helicopter flights in the first season, and a state Department of Environmental Quality decision in July denying the operators’ request for an exemption from DEQ review.

Why the review level matters

A categorical exclusion is a shortcut under the National Environmental Policy Act for actions an agency considers routine, with no significant effects. It needs little public documentation. An environmental assessment is a public analysis of whether a project would have significant effects. It ends either in a finding of no significant impact or in a decision to prepare a full environmental impact statement.

The forest said it will produce “one NEPA decision document that can support both federal and state permitting needs.” That would be a single analysis serving the Forest Service and Montana regulators.

The schedule is still being worked out. Sheep Creek is a FAST-41 transparency project, part of the federal program meant to make permitting timelines predictable. Montana joined that program earlier this month. The forest said it will work with cooperating agencies on an updated FAST-41 schedule that reflects the assessment. As of Tuesday, the dashboard listed none of the four review and permitting steps as complete and showed an estimated finish of Aug. 17, 2027. The U.S. Fish and Wildlife Service is the other federal agency with an action on the project.

The forest’s own project page still described the project as “Pre NEPA,” with a categorical exclusion as the expected analysis type, when checked Tuesday morning.

Reaction

US Critical Materials CEO Scott Osterman told the Daily Montanan that the company has already been doing the work an assessment requires and that the decision will have “no impact on our compliance work in progress.” The Bitterroot Water Partnership said the decision “facilitates greater transparency and public engagement,” according to the same report.

The valley’s economy also includes biotech employers such as Tonix Pharmaceuticals, which broke ground in Hamilton this fall. Much of the opposition to Sheep Creek has come from people who depend on the river, including fishing guides quoted in the Daily Montanan’s report.

How to follow it

The forest said its project inbox, Sheep.Creek.Comments@usda.gov, stays open throughout the review. It encouraged residents to watch the project webpage, the FAST-41 dashboard and future public notices. The forest has not said when a draft assessment will be released. More coverage is in our Energy & Environment section.